February 2006 - Oh my God what a nightmare and not a brick laid yet!

February 2nd 2006 

Have been contacted by SAUR to arrange a meeting at the site to discuss connecting the water.  Strangely, this only occurred after we chased the building company to find out if they had sorted this out yet.  Meeting went ok and they will be sending out their Devis in the next ten days - once this is approved it will take up to twenty five days for the work to be done.

Have finally arranged a meeting with the building company to discuss where this project is going - Ha Ha!

Having arranged this meeting and still being assured that our house will be ready by October 2006 we received a letter from our building company requesting the money (almost 20,000 Euros) to open the works.  At the bottom of this letter it stated that they will not be able to complete our house until at least April 2007!!!!!

It's going to be an interesting meeting tomorrow..................................